Dounreay end date that proved to be unachievable


By Alan Hendry

Register for free to read more of the latest local news. It's easy and will only take a moment.



Click here to sign up to our free newsletters!
A view of Dounreay from March 2018. Picture: Dounreay (a division of Magnox) and NDA
A view of Dounreay from March 2018. Picture: Dounreay (a division of Magnox) and NDA

The end of an era for Caithness... the last chapter in a pioneering industrial story that began in the black-and-white world of the 1950s... a final farewell to our great atomic age... Or at least, it would have been if a prediction made 11 years ago had proved to be accurate.

It was in May 2012 that Roger Hardy, then managing director of Dounreay Site Restoration Ltd (DSRL), announced a target for the demolition of the nuclear site that had transformed the county's socio-economic landscape over the course of six decades. Dounreay's operators were setting a specific end date of September 14, 2023.

That was when all redundant facilities needed to be flattened and the waste sorted, segregated and made safe for the long term, according to Mr Hardy. It was a big ask, he acknowledged at the time, but staff were responding to the challenge: "No-one seems hugely surprised by what we think is achievable."

It was destined not to be achievable after all. The current deadline for the clean-up is 2033, a full decade beyond that 2012 forecast – although questions have been raised as to whether even this revised schedule is a realistic one.

Earlier this year, ex-councillor Roger Saxon, a former chairman of Dounreay Stakeholder Group, expressed the view that 2033 would be unachievable. He was concerned that momentum had been lost on the decommissioning programme.

It was reported at the time that the Nuclear Decommissioning Authority (NDA), which owns Dounreay, was reviewing the processes and timescales behind the demolition of the experimental fast reactor complex.

Decommissioning work in progress in December 2017. Picture: Dounreay (a division of Magnox) and NDA
Decommissioning work in progress in December 2017. Picture: Dounreay (a division of Magnox) and NDA

The first site-wide decommissioning plan published in 2000 envisaged a 60-year programme of work. The latest NDA business plan projects the Prototype Fast Reactor being dismantled in 2027, with Dounreay's interim end state achieved in 2032/33.

Mr Saxon, a retired nuclear consultant, said in March: "I think it's a bit like the Scottish Government's schedule for dualling the A9 between Inverness and Perth. They kept with the 2025 date when it was obvious for a long time that could not be met.

He added: "I don't think it is worth getting hung up on having an exact end date. We just want to see progress and an assurance that the buildings are not going to be stuck in mothballs."

A spokesperson for DSRL said at the time: "The new long-range decommissioning plan is under review and is going through governance and assurance verification and will be communicated once approved."

The Dounreay dome under construction in the 1950s. Picture: Dounreay (a division of Magnox) and NDA
The Dounreay dome under construction in the 1950s. Picture: Dounreay (a division of Magnox) and NDA

Key dates in Dounreay's history (source: www.gov.uk):

1954 UK government selects wartime airfield at Dounreay as site for fast reactor research and development

1955 UK Atomic Energy Authority begins construction

1955 Craft apprentice training scheme starts

1955 The UK Atomic Energy Authority starts building housing estate in Thurso

1956 Ormlie Lodge staff hostel opens

1957 Nuclear reaction takes place for first time in criticality test cell

1957 Royal Navy announces submarine reactor test site named Vulcan

1957 Visits by the Queen Mother and the Duke of Edinburgh

1958 Materials Test Reactor goes critical

1958 Fuel reprocessing begins

1959 Experimental Dounreay Fast Reactor goes critical

1962 First electricity exported to National Grid

1966 Construction begins of Prototype Fast Reactor

1969 Materials Test Reactor shuts down

1974 Prototype Fast Reactor goes critical

1977 Experimental fast reactor shuts down

1977 Explosion in underground waste shaft

1983 Radioactive particles discovered on beaches

1986 BNFL and UKAEA announce plan to build European Demonstration Reprocessing Plant

1988 UK government announces withdrawal from fast reactor technology

1994 Prototype Fast Reactor shuts down

1996 Fuel reprocessing stops

1998 Safety audit by regulators identifies 143 recommendations for improvement

2000 UKAEA publishes site closure plan

2004 Fuel fabrication stops

2007/8 Nuclear Decommissioning Authority inherits site and Dounreay Site Restoration Ltd becomes its operator

2012 Management contracted out to Babcock consortium

2015 Removal of plutonium and uranium begins

2021 NDA takes management in-house

2023 Dounreay becomes a division of Magnox Ltd

Control room image from the Dounreay archives. Picture: Dounreay (a division of Magnox) and NDA
Control room image from the Dounreay archives. Picture: Dounreay (a division of Magnox) and NDA